Client: Kier Construction Group Ltd
Value: £875,000.00
Works Package:
Construction of a four steel frame building with a reinforced concrete basement car park. The works package consisted of all groundworks, drainage, foundations, water proof and gas proof membranes, basement retaining walls, basement columns, basement brush finished slabs, ground level podium slab and reinforced concrete slabs to the upper floors with power float finish slabs.
Quantities:
- 260.00 m of foul and stormwater drainage
- 2,100.00 m2 of combined gas and waterproof membrane
- 1,810.00 cu m concrete
- 218.00 tn reinforcement
- 2,900.00 m2 of Mesh Reinforcement
- 180.00 m2 of column formwork
- 1,620.00 m2 of wall formwork
- 1,100.00 m2 of soffits of slabs formwork
- 3,000.00 m2 of power float finish slabs
- 1,000.00 m2 brush finish slabs