Birmingham New Street Station Redevelopment:
Client: Volker Fitzpatrick Ltd
Value: £135,000.00
Works Package:
Construction of a new reinforced concrete floor to the East Void works, consisting of all formwork make ups around pre-cast flooring units, fixing of reinforcement and placement of concrete with power float finish.
Quantities:
- 280.00 cu m concrete to floors
- 1,280.00 m2 of power float finish to floors
- 68.00 tn of reinforcement
- 1,280.00 m2 of mesh reinforcement
Weekend and Night time possession works carried out.